Bonding is one of the most misunderstood requirements in the GC-subcontractor relationship. General contractors on public projects in Florida are required to carry payment and performance bonds by law (Florida Statute 255.05 for public construction). On private commercial projects, bonding is negotiated. Many GCs skip it entirely on private work because it adds cost and creates friction at subcontractor qualification.

That is a mistake that occasionally becomes an expensive one.

Commercial planning workspace with abstract plans and estimating tools
Editorial illustrationBonding and qualification start with a defined scope, responsible parties, and documentation that can be reviewed. Good paperwork reflects real capacity rather than a generic promise.

What Bonds Actually Do

A performance bond guarantees that the sub will complete the contracted scope. If the sub defaults — abandons the project, goes out of business mid-project, or is terminated for cause — the surety steps in to either fund the completion with a replacement contractor or pay the GC the cost to complete.

A payment bond guarantees that the sub pays its own suppliers and lower-tier subs. This protects the GC from materialman liens filed against the project by vendors who supplied materials to the sub but were not paid.

Without a payment bond, a sub's financial trouble becomes the GC's legal problem. Florida's lien law (Chapter 713) allows unpaid suppliers and lower-tier subs to file liens directly against the owner's property, even if the GC paid the sub in full. A payment bond cuts off that lien exposure.

High-bay warehouse shell with steel frame and concrete slab
Editorial illustrationLarger commercial work combines structure, schedule, and trade coordination. A subcontractor's package should make its exclusions, interfaces, and manpower plan clear before work is awarded.

When JK Requires Bonds from Trade Subs

JK Prestige structures bonding requirements based on contract value and project type:

Always required:

Evaluated case-by-case:

Generally not required:

What a Bond Costs and Who Pays It

Bond premiums are set by the surety and vary based on the sub's creditworthiness and the project risk profile. Typical ranges:

On a $400,000 MEP subcontract, a bond premium runs $2,000 to $6,000. JK's position: the bond premium is a cost of doing the project correctly, not an optional add. When bonding is required, it is included in JK's subcontract and the sub is expected to carry it in their bid.

If a sub's bid does not include bonding and JK's scope requirements include it, the sub's bid is not apples-to-apples with a bid that does. JK notes this at bid review and requests a revised bid with bonding included.

If a Sub Cannot Get Bonded: What That Tells You

The surety industry is the original project underwriter. If a sub cannot obtain a performance and payment bond from a licensed surety, it typically means:

Any of these conditions should give a GC pause before awarding a significant subcontract. A sub that cannot get bonded is a sub that a neutral third party has assessed as financially risky.

This is not an automatic disqualifier — JK has worked with strong subs who simply had not yet established a bond relationship. But it is a flag that triggers additional pre-qualification: financial statements, bank references, list of current projects and their remaining backlog.

Residential addition framing and roof tie-in at an existing wall
Editorial illustrationEven smaller scopes have consequential interfaces. Clear responsibility for framing, flashing, permits, and inspection protects the owner and the trade partner alike.

How Bonding Interacts with Subcontract Language

A bond is only as useful as the subcontract it is attached to. If the subcontract does not clearly define the scope, schedule, and payment milestones, the bond becomes harder to call. Sureties investigate claims carefully before paying — a vague subcontract gives the surety room to dispute the claim.

JK's subcontracts are written with specific scope attachments, a defined schedule of values, clear payment milestones, and a defined default and cure process. The bond attaches to that contract and the surety's obligation is defined by its terms.

Alternatives When Bonding Is Not Practical

On smaller commercial subcontracts or residential scopes where bonding is not practical, JK uses other protection mechanisms:

Joint check agreements. JK and the sub agree that material suppliers will be paid by joint check (cosigned by both JK and the sub), ensuring that materials are actually paid for and cannot generate a lien.

Retainage. JK holds 10 percent retainage on subcontract payments through substantial completion. Retainage creates an incentive for the sub to finish the project and provides a reserve against the cost of corrections.

Conditional final payment. The final payment to the sub is conditioned on a lien release and waiver from the sub and, on larger projects, from any known material suppliers.

These mechanisms do not replace a bond, but they reduce lien exposure and create financial accountability on smaller projects where full bonding is disproportionate.

Get a written estimate in 48 hours.

No call center. No coordinator. A JK principal reviews every inquiry and replies with a real number, not a range, not a follow-up form.

Request Free Estimate →

Frequently Asked Questions

Are GCs required to bond their subcontractors in Florida?
On public projects in Florida, bonding requirements are established by Florida Statute 255.05 and apply to the GC's bond with the owner. Whether the GC requires sub-bonds is a contract matter. On private commercial projects, bonding of subs is negotiated and not legally required.
What is the difference between a performance bond and a payment bond?
A performance bond guarantees that the sub completes the contracted work. A payment bond guarantees that the sub pays its suppliers and lower-tier subs. JK requires both on bonded subcontracts — a payment bond without a performance bond (or vice versa) provides only partial protection.
Does JK Prestige carry its own bonds on commercial projects?
Yes. JK carries performance and payment bonds on commercial projects where required by the owner or the project financing structure. JK's bonding capacity is available through our surety on projects up to $5 million per project and higher on a case-by-case basis.
How do I know if a potential sub can be bonded?
Ask directly during pre-qualification. A sub with an established bond program can typically provide a letter of bonding capability from their surety within a few days of request. A sub who cannot provide this letter within a week likely cannot be bonded.
Should I require bonds on residential subcontracts in Florida?
Bonding is rarely practical on residential subcontracts under $50,000. The premium cost is disproportionate and most residential subs do not maintain bond programs. For residential projects, retainage, joint checks, and conditional final payment are more practical protection mechanisms. --- Looking for a self-perform GC partner in Florida who carries their paperwork? JK Prestige delivers credentialed, bonded trade crews for framing and drywall on commercial and industrial projects. Call to discuss qualification requirements.