You collected two bids on your kitchen renovation. One is $95,000. One is $125,000. The instinct is to call the lower number and start asking for a discount. That instinct produces bad outcomes more often than not.

Two bids on the same project are almost never bids on the same scope. Allowances — those placeholder dollar amounts for tile, fixtures, and cabinets — are usually different. One contractor includes permits; one does not. One contractor self-performs framing and drywall; one brokers everything to subs with a 15–20% markup. One contractor has a $0 retainage clause; one holds 10%.

Bid comparison is not arithmetic. It is a scope-alignment exercise that usually requires a direct conversation with each contractor. Here is how to do it correctly.

Abstract plans, finish samples, blank documents, and measuring tools in an unoccupied kitchen renovation
Editorial illustrationA kitchen renovation planning table establishes the drawings, selections, and scope records needed before two bids can be compared.

Step 1: Confirm Both Bids Cover the Same Scope

Before you compare a single number, read both bids line by line and identify what each one explicitly includes and excludes. Pay attention to the exclusions list — it is often longer than the inclusions list, and it is where the price difference lives.

Common scope gaps between bids on the same project:

Mark every line that differs between the two bids. Do not compare total numbers until both bids cover identical scope. If a scope gap exists, call each contractor and ask for a revised number that includes the missing item. This step alone usually closes 30–50% of the apparent price gap.

Blank estimate grids, finish samples, scale ruler, pencil, and calculator on a planning table
Editorial illustrationEstimate grids, samples, and a calculator support line-by-line comparison of allowances against realistic material selections.

Step 2: Compare Allowances Line by Line — This Is Where Bids Lie

Allowances are the most misunderstood part of a construction bid. An allowance is a placeholder amount for an item that has not yet been selected — tile, plumbing fixtures, light fixtures, appliances, cabinetry. The contractor is not promising to build the project for the total bid price; they are promising to apply the allowance amount toward those items.

If your actual selections exceed the allowance, you pay the difference. If they come in under, you get a credit.

A classic scenario: Contractor A bids a kitchen renovation at $95,000 with a $12,000 cabinet allowance. Contractor B bids $118,000 with a $28,000 cabinet allowance. Semi-custom cabinets for a 12-foot run cost $22,000 installed. With Contractor A, you owe a $10,000 change order on cabinets alone. Total actual cost: $105,000. With Contractor B, you get a $6,000 credit. Total actual cost: $112,000. The gap between bids has narrowed to $7,000 — and Contractor B has a more accurate number.

Request that both contractors use the same allowance amounts based on your actual selections or a defined product tier. That is the only way to make the comparison valid.

Step 3: Compare Contingency Structure — Who Carries the Risk?

Some fixed-price bids include a built-in contingency line (typically 5–10% of construction cost) that the contractor carries as risk protection against unforeseen conditions. Others do not include a contingency — meaning any unforeseen condition triggers a change order.

Ask each contractor: "What happens if you open the wall and find rotted framing or old galvanized pipe that needs replacement? Is that covered in your price, or does it come as a change order?"

The answer reveals the contract's risk structure. A contractor who says "that would be a change order" is not hiding anything — unforeseen conditions are a legitimate category of extra cost. But the structure of how that conversation happens matters. Do you see a written change order with itemized cost before work continues? Or do you get a phone call with a verbal number while demo is mid-stream and you feel pressure to approve?

Ask for the change order clause in writing. It should specify: written change order required before any additional work, owner signature required, and work stops (or does not proceed) pending owner approval.

Step 4: Check Payment Schedule — Front-Loaded Terms Are a Warning Sign

A construction payment schedule should track closely with work completed. You should be paying for value received, not advancing funds for work not yet done.

A reasonable payment schedule for a $100,000 residential renovation looks something like:

A front-loaded payment schedule — where a contractor requests 30–50% upfront before significant work is completed — is a warning sign. It either indicates cash flow problems (the contractor needs your money to pay for other jobs), poor business management, or in the worst case, a contractor who collects a large deposit and disappears.

In Florida, unlicensed contractor fraud almost always involves large upfront payments. The Florida Construction Lien Law (Chapter 713) does not protect you from a contractor who takes your deposit and leaves — it governs liens on completed work, not deposit theft.

Compare the payment schedules of both bids. If one is front-loaded, ask why.

Step 5: Look at Warranty Terms

Contractor workmanship warranties vary widely. Standard terms in Florida residential construction run 1 year on workmanship, with manufacturer warranties passing through on products and materials. Some contractors offer extended warranties on specific systems — roofing, waterproofing, HVAC installation.

Read the warranty clause in both bids. Ask:

A contractor who offers a 1-year workmanship warranty and no clarity on the claim process is offering less than one who offers the same term with a defined response time and written escalation path.

Step 6: Verify Who Pulls Permits — Non-Negotiable in Florida

The contractor of record on a Florida building permit is the licensed professional legally responsible for the work meeting code. Ask both bidders: "Will you pull all permits for this project under your license?"

If either contractor suggests that you pull permits as owner-builder, or that permits are not required for this scope, resolve that question immediately with Duval County Building Services before proceeding. Owner-builder permits are intended for homeowners who perform their own work — not for owners hiring contractors. A contractor who works under an owner-builder permit is avoiding accountability.

Verify that permits will be posted on site before demo begins, and that all required inspections are scheduled and completed before walls close.

Unoccupied framed interior with coordinated plumbing, electrical wiring, and metal ductwork
Editorial illustrationVisible framing, plumbing, electrical, and ductwork show the trade coordination a general contractor must manage during construction.

Step 7: Ask Who Does the Actual Work — Self-Perform vs. All Brokered

A general contractor who self-performs framing, drywall, finish carpentry, and concrete has more cost control and schedule accountability than one who brokers every trade to subcontractors at a markup.

Ask both contractors: "Which trades do your employees perform, and which do you subcontract?"

Self-performing trades typically include framing, concrete, rough carpentry, drywall, and finish carpentry. Specialty trades — plumbing, electrical, HVAC, tile, roofing — are often subcontracted even by large GCs. The key question is whether the GC is adding value through project management and scheduling, or primarily marking up subcontractor prices.

A GC who self-performs 60–70% of a project's labor has more flexibility to manage cost, schedule, and quality than one who is entirely dependent on subcontractor availability and pricing. JK Prestige self-performs framing, concrete, drywall, finish carpentry, and roofing — which means direct accountability on the majority of labor hours on most projects. See the JK Prestige approach.

Step 8: The Lowest Bid Is Rarely the Best Bid

A low bid is a promise about what a project will cost. It is not a guarantee unless it is backed by a fixed-price contract with a clearly defined scope, accurate allowances, and a clear change order clause.

The lowest bid on a residential project is often lowest for one of four reasons:

  1. Scope omissions: Items are missing from the bid that will appear as change orders later.
  2. Low allowances: The allowances are not realistic for any material selection the owner would actually make.
  3. Subcontractor dependence: The contractor plans to bid out all trades after winning the job and hopes the subcontractor market cooperates.
  4. Contractor desperation: A contractor with cash flow problems bids low to win work and funds earlier projects with your deposit.

None of these is a reason to choose the higher bid automatically. But each is a reason to ask follow-up questions before signing. Ask the low bidder to explain the gap. A legitimate low bidder can explain exactly where their number differs — lower overhead, a different material source, self-performed labor. If the explanation is vague, that is the answer.

See how JK Prestige structures transparent, itemized fixed-price proposals to make comparison clear.

Get a written estimate in 48 hours. Call (904) 944-0278 or request a consultation.

Get a written estimate in 48 hours.

No call center. No coordinator. A JK principal reviews every inquiry and replies with a real number, not a range, not a follow-up form.

Request Free Estimate →

Frequently Asked Questions

Why should not I just pick the lower of two bids?
Two bids on the same project are almost never bids on the same scope, since allowances, permit inclusion, self performed versus subcontracted trades, and retainage terms typically differ between contractors. Read both bids line by line, mark every difference, and call each contractor for a revised number that matches scope before comparing totals, a step that alone often closes 30 to 50 percent of the apparent price gap. Comparing totals before aligning scope is comparing two different projects, not two prices for the same one.
How do allowances distort a bid comparison?
An allowance is a placeholder amount for something not yet selected, like cabinets or tile, so the lower total bid can have the smaller allowance and end up costing more once you make real selections. For example, a bid with a 12,000 dollar cabinet allowance against actual semi custom cabinet costs of 22,000 dollars means a 10,000 dollar change order later, while a bid with a 28,000 dollar allowance for the same cabinets nets a credit. Ask both contractors to use the same allowance amounts based on your actual selections so the comparison is valid.
What does a front loaded payment schedule tell me about a contractor?
A payment schedule should track closely with completed work, so something like 10 percent at signing followed by milestone based draws through substantial completion is reasonable. A contractor who wants 30 to 50 percent upfront before significant work happens is showing a warning sign that can indicate cash flow problems, poor business management, or in the worst case, a contractor who takes a large deposit and disappears. Ask directly why a bid is front loaded if you see one.