A kitchen renovation is the most disruptive project most homeowners ever tackle. You lose your kitchen for weeks, you make decisions under pressure, and every trade stacks on top of the one before it. Do it in the right order and the job flows. Do it out of order and you end up tearing out finished work.

This guide is for the homeowner who wants to understand the full scope before calling contractors, or who genuinely plans to self-manage portions of the work. Difficulty: moderate to high. Timeline: 4 to 10 weeks depending on scope. Total cost range: $15,000 to $75,000 for a typical Jacksonville kitchen, depending on size, finishes, and how much structural work is involved.

Kitchen cabinet run being aligned level during renovation
Editorial illustrationSet the renovation sequence around layout, services, cabinets, and countertop dependencies. Finishes land better when the boxes and utility locations are already verified.

Tools You Need

Materials You Need

Costs below are rough Jacksonville-area estimates for mid-grade materials.

Kitchen backsplash tile laid out on a prepared wall
Editorial illustrationPlan finish work after the larger cabinet and countertop decisions are stable. Tile, paint, and trim should complete the kitchen rather than force a change to the underlying layout.

Step-by-Step Instructions

Phase 1: Planning and Permits

Step 1: Lock your layout before you buy anything.

Most kitchen mistakes happen at the planning stage. Before ordering cabinets or scheduling demo, nail down every decision: cabinet layout and dimensions, appliance specs (especially the range hood rough-in height and refrigerator depth), countertop material, sink location, and lighting plan.

In Jacksonville and Duval County, a permit is required any time you move plumbing, move electrical panels or add circuits, remove a load-bearing wall, or change the exterior envelope. Pull the permit before work starts. Inspectors here are active, and unpermitted kitchen work will complicate your sale. Apply through the City of Jacksonville Building Inspection Division online portal. Budget two to four weeks for permit approval.

Measure your kitchen three times. Draw it to scale. Confirm that your cabinet order matches your actual wall dimensions, not the nominal dimensions from the builder floor plan.

Step 2: Order materials with lead time in mind.

Semi-custom cabinets take four to ten weeks. Countertops are templated after cabinets are installed, then fabricated in one to two weeks. Appliances from major retailers can take two to six weeks for delivery. Order everything before demo starts so materials arrive in sequence.

Phase 2: Demo and Rough Work

Step 3: Demo the kitchen.

Shut off the water supply at the main or at the shutoffs under the sink. Turn off the breakers for the kitchen circuits at the panel. Photograph all existing plumbing and electrical before touching anything.

Remove appliances first. Disconnect the dishwasher water supply and drain line. Pull the range. Cap the gas line if present — this is not a DIY step unless you are a licensed plumber. Cap water lines.

Remove upper cabinets first, then lower cabinets. Cabinets are typically screwed into studs through a mounting rail. Use the drill to back out screws; do not pry them loose unless you plan to replace the drywall.

Remove the countertop by cutting any caulk at the wall seam and working a pry bar under the front edge. Disconnect the sink drain and supply lines first.

Bag and haul debris as you go. A 10-yard dumpster handles most kitchen demos.

Step 4: Rough plumbing and electrical.

If you are moving the sink location or adding a pot-filler line, rough plumbing goes in now. A licensed plumber must perform this work in Florida and pull the plumbing permit separately.

Electrical rough-in covers adding circuits for the dishwasher (dedicated 20A), garbage disposal (15A dedicated), microwave or range hood (dedicated 20A), refrigerator (dedicated 20A), and any GFCI-protected counter outlets. The National Electrical Code requires GFCI protection on all kitchen counter-level outlets. Your electrician will also run any wiring for under-cabinet lighting. Licensed electrician required in Florida.

Do not close walls until inspections pass.

Step 5: Rough HVAC if needed.

If you are adding or relocating an island exhaust hood with exterior venting, the duct rough-in happens now. Confirm duct sizing matches the hood's CFM rating. In Jacksonville's humid climate, exterior venting is essential — recirculating hoods are a band-aid.

Phase 3: Walls, Floors, and Prep

Step 6: Close walls and prep surfaces.

After rough inspections pass, hang drywall or repair existing drywall. Use moisture-resistant drywall (MR board or greenboard) behind the backsplash area. Tape, mud, and sand. Prime all new drywall before painting.

Install flooring before lower cabinets if you want a clean look and easy future cabinet replacement. Install flooring after cabinets if you want to use less material and are confident the layout will never change. Either approach is acceptable; just decide before you order.

Phase 4: Cabinets and Countertops

Step 7: Install upper cabinets before lower cabinets.

This is the rule that most DIYers get backwards. Uppers installed first means you are not leaning over base cabinets, and you have access to the wall for your ledger board.

Snap a level line on the wall at the bottom of your upper cabinet run. Screw a temporary ledger board (a straight 1x4) to this line to support the cabinet weight while you fasten it. Find every stud and mark them clearly with tape. Upper cabinets fasten through the mounting rail into studs with 3-inch screws. Clamp adjacent cabinets together face-to-face before drilling pilot holes for connection screws, so faces stay flush.

Step 8: Install base cabinets.

Find the high point of your floor. Set your first base cabinet at the high point and shim all subsequent cabinets to that level. A kitchen floor that is a half-inch out of level across 12 feet will produce doors that swing open or closed on their own and countertops that look tilted. Take the time to shim and level before fastening.

Connect cabinets face-to-face the same as uppers. Fasten to studs through the back mounting rail and through the toe kick.

Phase 5: Countertops, Backsplash, and Fixtures

Step 9: Template and install countertops.

After cabinets are set and final, call the countertop fabricator for templating. They will take precise measurements and create a digital or physical template. Fabrication takes one to two weeks. Countertops are set in place and fastened with construction adhesive and small brackets. The sink cutout is made by the fabricator based on your sink dimensions.

Step 10: Set plumbing and electrical trim.

After countertops are in, your plumber sets the sink, connects the drain and supply, and installs the garbage disposal and dishwasher supply line. Your electrician installs outlet covers, switch plates, under-cabinet lighting, and the dishwasher circuit connection.

Step 11: Install backsplash tile.

See the separate backsplash guide for full detail. At minimum: use a notched trowel and polymer-modified thinset, keep grout joints consistent, and seal natural stone before grouting. Allow 24 hours before grouting, 72 hours before sealing.

Phase 6: Finish Work

Step 12: Paint, hardware, and punch list.

Paint walls before installing appliances. Two coats of a quality eggshell or satin finish. Install cabinet hardware after paint is dry. Set and level appliances. Install the range hood and connect venting. Caulk at all wall-to-counter seams and wall-to-cabinet seams with a paintable siliconized acrylic. Walk the space and write a punch list of everything incomplete before calling the job done.

Common Mistakes to Avoid

Kitchen sink base with accessible plumbing connections
Editorial illustrationLeave access for water, drains, appliances, and future service as the room comes together. A renovation is successful when the finished kitchen is both usable and maintainable.

When to Hire a Pro Instead

You should bring in a licensed contractor for any of the following:

Need a Jacksonville GC for this job? Get a 48-hour free fixed-price estimate from JK Prestige Constructor.

Get a written estimate in 48 hours.

No call center. No coordinator. A JK principal reviews every inquiry and replies with a real number, not a range, not a follow-up form.

Request Free Estimate →

Frequently Asked Questions

How long does a kitchen renovation take in Jacksonville?
A full gut renovation with new cabinets, countertops, plumbing, and electrical typically takes six to ten weeks from demo to punch list. Simpler refreshes — paint, hardware, and a countertop swap — can be done in one to two weeks. Permit timelines in Duval County add two to four weeks before work starts.
Do I need a permit to renovate a kitchen in Jacksonville FL?
Yes, if you are moving plumbing, adding or relocating electrical circuits, or removing walls. A cosmetic renovation (paint, cabinet hardware, new countertop on existing substrate) generally does not require a permit. When in doubt, call the City of Jacksonville Building Inspection Division and describe the scope. It takes five minutes and saves a lot of headaches.
What is the most common reason kitchen renovations go over budget?
Scope creep after demo. Once you open walls, you often find water damage, outdated wiring, or plumbing that needs replacement. Budget a 15 percent contingency on every kitchen job, minimum.
Should I live in my home during a kitchen renovation?
You can, but plan for it. You will be without a kitchen for three to eight weeks. Set up a microwave, hot plate, and mini-fridge somewhere else in the house. Dust migration is significant during demo and drywall phases — close off the space with plastic sheeting.
How much does a kitchen renovation cost in Jacksonville FL?
Mid-grade renovations (semi-custom cabinets, quartz countertops, standard appliances) run $25,000 to $50,000 in the Jacksonville market as of 2025. Budget renovations using stock cabinets and laminate countertops can come in at $15,000 to $20,000. High-end custom kitchens with structural changes exceed $75,000.
What order should I renovate my kitchen?
Demo first, then rough mechanical (plumbing, electrical, HVAC), then wall and floor prep, then cabinets, then countertops, then tile, then fixtures, then paint and trim, then appliances. This sequence exists because each trade depends on the one before it being complete and inspected.