On most commercial construction projects, submittals and RFIs are managed by the GC and tracked in a master log. Trade subs are expected to submit their required documents on schedule, respond to GC comments, and maintain a clear record of field questions that need design team clarification.

In practice, many framing and drywall subs in Florida treat submittals and RFIs as GC problems. They wait for the GC to chase them for shop drawings. They call the GC foreman when they find a drawing conflict instead of writing a formal RFI. They miss the submittal schedule dates in the subcontract and expect the GC to absorb the delay.

JK Prestige operates differently. Here is what GC partners should require — and what JK delivers as standard.

Commercial planning workspace with abstract drawings, laptop, and hardhat
Editorial illustrationA useful submittal and RFI process turns unanswered field questions into tracked decisions. The objective is to resolve details before they become change orders or rework.

What Submittals Are Required from a Framing or Drywall Sub

The specific submittal requirements for a trade sub are defined in the project specifications (Division 01 for general requirements and the relevant technical sections for each trade). For framing and drywall, typical required submittals include:

Cold-formed metal framing (Division 05 40 00):

Gypsum board assemblies (Division 09 29 00):

JK submits all required documents in the format specified by the project (PDF submittals to Procore or Submittal Exchange, or paper submittals on projects that require it) within the schedule dates established in the subcontract.

Commercial fit-out with bar framing and coordinated plumbing and electrical rough-in
Editorial illustrationComplex interiors show why coordination matters: equipment, plumbing, electrical, and finishes all compete for the same space. RFIs should clarify the intended assembly before trades build past the conflict.

Submittal Schedule: How JK Manages It

At subcontract execution, JK reviews the required submittals against the project master schedule and establishes submittal due dates working backward from the required approval dates. A submittal that must be approved before framing begins needs to be submitted 4 to 6 weeks before framing mobilization — not the week before.

JK maintains its own submittal log with tracking fields for:

The GC receives a copy of JK's submittal log at each weekly report. This means the GC sees the same tracking data JK uses internally — there is no information asymmetry about what has been submitted and what is pending.

How JK Writes RFIs

An RFI (Request for Information) is the formal mechanism for asking the design team a question about the contract documents. RFIs should be written when:

An RFI is not a vehicle for negotiating scope changes. It is a documentation mechanism. JK writes RFIs with:

Clear question: One specific question per RFI. Not "see attached photos for multiple issues" but "At grid C4-C5 on floor 3, the structural drawings show a 3-1/2" stud wall but the MEP drawings show a 5-inch pipe running in the same stud cavity. What is the design intent for stud depth at this location?"

Reference to documents: Drawing sheet number, detail reference, and spec section that applies.

Proposed answer: JK's field recommendation for how to resolve the conflict. The design team can accept the proposed solution, modify it, or reject it — but providing a proposed answer accelerates the response time.

Dates: Date submitted. Required response date (stated explicitly). Late responses that affect the work are noted in the daily report and on the schedule.

What GC Partners Can Expect from JK on the RFI Log

JK does not send RFIs verbally. Every field question that requires a design team response gets a formal written RFI through the GC.

JK does not pile multiple questions into a single RFI. One question, one RFI. This allows the design team to assign each RFI to the right discipline and respond without coordinating multiple sub-questions.

JK tracks open RFI response time. If an RFI is open past the requested response date and the work is on the critical path, JK flags it in writing to the GC with a specific statement: "RFI [number] is 5 days past the requested response date. If a response is not received by [date], the following work will be delayed: [description]. Please confirm status."

Addition roof tie-in with visible flashing and framing coordination
Editorial illustrationInterfaces between new and existing construction are especially sensitive to incomplete information. Detail approvals should protect the water, structure, and finish sequence before work proceeds.

What Happens When Submittals Are Late (From Any Party)

Submittal delays create downstream schedule impacts. If JK submits a shop drawing late, the GC's review period is compressed. If the design team returns it late, JK's procurement lead time is compressed. The party who caused the delay owns the schedule impact.

JK maintains a documented record of all submittal submission dates and return dates. If the GC's or design team's review period extended beyond the contract-allowed turnaround time (typically 10 to 14 business days on commercial projects), and that extension affected JK's material procurement or mobilization, JK provides written notice within 48 hours of receiving the late return.

This is not adversarial. It is the documentation discipline that prevents disputes at project closeout.

Get a written estimate in 48 hours.

No call center. No coordinator. A JK principal reviews every inquiry and replies with a real number, not a range, not a follow-up form.

Request Free Estimate →

Frequently Asked Questions

What submittal types does a framing sub typically need to provide?
Shop drawings, product data, and fire/sound test reports are the most common. The specific requirement list is in Division 01 of the project specifications. JK reviews the full submittal requirement list at subcontract review and builds a submittal schedule before mobilization.
What is the difference between a submittal and an RFI?
A submittal is a document the sub provides to demonstrate that their proposed materials and methods comply with the contract requirements (shop drawings, product data, test reports). An RFI is a question to the design team asking for clarification on something unclear or conflicting in the contract documents. They are separate log items with separate tracking.
How does JK submit documents on Procore?
JK is experienced with Procore's submittal and RFI modules. JK receives an invitation to the project Procore site, sets up the trade partner account, and submits all required documents through the Procore workflow. No parallel paper submittals unless the GC specifically requires it.
What happens if JK receives an RFI response that changes the scope of work?
If the design team's RFI response requires work that was not in the original scope, JK identifies the change and submits a written change order request to the GC within 5 business days of receiving the response. The change order request includes the specific scope addition or credit, the basis for pricing, and the schedule impact if any.
How long does JK take to submit required shop drawings?
JK targets submittal of all required shop drawings within 10 business days of subcontract execution, for fabrication items that require long lead time. For standard framing submittals, the schedule is coordinated with the project master schedule. JK has never been the reason a submittal log was behind on a project. --- Looking for a framing or drywall trade partner in Florida who manages their own documentation? JK Prestige handles submittals, RFIs, and daily reports to a commercial GC standard. Call to discuss qualification.